O-Train trains now run to Trim in full-line testing, but riders still get off at Blair
O-Train Line 1 trains began running the full length of the line between Tunney's Pasture and Trim stations on Sunday as OC Transpo moved into full-line testing of the long-awaited East Extension — though passengers must still leave the train at Blair Station.

Ottawa's O-Train East Extension took another step toward opening this week as OC Transpo began running Line 1 trains along the full route between Tunney's Pasture and Trim stations as part of a new phase of testing.
The testing began Sunday, Nov. 22, the City of Ottawa said in a notice issued Nov. 20. While eastbound trains continue past Blair Station and display Trim as their destination, the extension is not yet open to passengers, and customers must disembark at Blair.
What riders will notice
According to the city, Line 1 customers can expect several changes during the testing period:
- Destination signs and next-departure displays showing Trim Station as the final eastbound stop, even though riders must exit at Blair;
- More frequent train service at certain times as part of testing activities;
- Occasional double-car trains on weekends;
- Updated station signage and wayfinding identifying Trim as the line's new eastern terminus.
OC Transpo staff are being posted at Blair Station to help customers.
Why full-line testing matters
The city described full-line testing as a key step before the final phases required to open the East Extension, which will carry O-Train service into Orléans. During this phase, OC Transpo tests vehicles, schedules and staffing assignments across the whole line, part of a staged approach meant to exercise the full system and identify any needed improvements. The city noted the same approach was used before the launches of O-Train Lines 2 and 4.
The testing is expected to continue for a few weeks. The city cautioned that it may turn up issues that Rideau Transit Maintenance (RTM) or East-West Connectors (EWC), the extension's builder, need to address, which could affect train operations between Blair and Trim.
Pause the week of Nov. 29
At EWC's request, trains will not operate on the new East Extension during the week of Nov. 29 so crews can advance upgrades to track infrastructure intended to improve system reliability. Full-line testing will resume once that work is complete.
The city called the interruptions "a normal part of the testing process" and said its priority remains maintaining existing Line 1 service. No opening date for passenger service on the extension was given in the notice.
Source: City of Ottawa — "O-Train East Extension full-line testing starts November 22", Nov. 20, 2026.